Environmental clearance from Ministry of Environment & Forests has been received on 30th January 2008
31/01/08
Signing of the contracts for BF package with SSIT on
|
Sr. No |
Milestone |
Date |
|
1 |
Incorporation of company |
January 4, 2007 |
|
2 |
Possession of land |
June 7, 2007 |
|
3 |
MOU with Maharashtra Government |
June 18,2007 |
|
4 |
Ordering of rolling mill package |
August 1, 2007 |
|
5 |
Appointment of MN Dastur as main consultant |
October 6, 2007 |
|
6 |
Environmental Clearance |
January 30, 2008 |
|
7 |
Ordering of Blast Furnace Package |
January 31, 2008 |
|
8 |
Ordering of Sinter Plant Package |
January 31, 2008 |
|
9 |
Ordering of Captive Power Plant Package |
June 12, 2008 |
|
10 |
Ordering of Steel Melt Shop Package |
September 2008 |
|
11 |
Consent to Establish from Maharashtra Pollution Control Board |
March 12, 2009 |
|
12 |
Ordering of ASU Package |
May 23, 2009 |
|
|
|
|